The 'breaking ground' date of the 02 Jun 2010 was the start of the project and the house was handed over from the builder as a new build on the 03 Dec 2010 once the payment for the house had gone through. Six months, start to finish for this stage of the building.

The new build status meant that the house structure was finished, kitchen and bathrooms all finished, all walls and ceilings painted, water and electricity all switched on and boiler working but other than that it was a blank canvas to be made into a home.

First job, build the replacement shed further down the garden 

Very pleased with the result - now to empty the old kennels

04 Jun: The cleared ground after 02 Jun demolition day

11 Jun: Foundations dug and filled, pipework going in now

18 Jun: Brickwork foundations being laid ready for blocks

18 Jun: The chimney for the inglenook starts to rise

21 Jun: Block foundations laid and house shape develops

06 Jul: Filming of the first of the house frames slotted into place

07 Jul: Ground floor frame in place, scaffold being erected

08 Jul: First floor frame being erected and scaffolding built up

13 Jul: Frame up and waiting for the roof trusses to be fitted

14 Jul: Roof timbers starting to be put into place now

14 Jul: ORANGE front door in - told builder we asked for OAK!

14 Jul: French doors in, one set not as wide so put into kitchen

15 Jul: The inglenook starting to be built up outside the frame

17 Jul: Builder's drawing of the inglenook on inside of frame

17 Jul: The base wall on the house exterior being built

18 Jul: Inglenook being built, as seen from the lounge area 

21 Jul: Battening to take the wire frame for the rendering 

21 Jul: Brickwork being built up in the lounge for the inglenook

28 Jul: Roof battens in place for tiling to begin shortly

29 Jul: Tiles being thrown up and stacked, ready for use

01 Aug: Tiles on the main part of the roof, slates for annex

03 Aug: Whimsical oak beams for the vaulted bedroom ceiling

04 Aug: Vaulted bedroom non-structural ceiling beams in place

07 Aug: Electrical wiring and networking being installed

10 Aug: Oak beam for inglenook in place and brickwork complete

10 Aug: First fix plumbing, electrical and networking done

11 Aug: Wiring coming down into that hallway cupboard

11 Aug: RCD Consumer Unit wires, understairs eventually

14 Aug: Ray in inglenook, note three brick depth at base

20 Aug: First render layer going on over the wire panelling

22 Aug: Beautiful detail at the top of the inglenook chimney

22 Aug: School holidays but Ray is absolutely exhausted

24 Aug: Trying out different external paint colours

25 Aug: Insulation packed into walls and ceilings and fixed in

02 Sep: First coat of render on and waiting for fine 2nd coat

03 Sep: Drylining boards being fitted over battens and cladding

06 Sep: Top coat of render has been applied to upper house

20 Sep: Rear of the house rendered, top and bottom

10 Sep: Organising electricity to go underground in the garden

14 Sep: Rendering painted the chosen Sandtex Beige

18 Sep: Slates being put onto roof to make it look an add-on

21 Sep: Electricity and water all ready in the soon to-be kitchen

23 Sep: The house is revealed as the scaffold is taken down

27 Sep: Underfloor heating pipework and networking cables

27 Sep: The underfloor heating cables throughout ground floor

05 Oct: RCD Consumer Unit which will be understairs soon

05 Oct: At last! A replacement for the ORANGE front door

08 Oct: The kitchen starts to be fitted by expert carpenters

11 Oct: The stairs arrive to be fitted, no longer a ladder

11 Oct: An electricity pole erected for over-road cabling

11 Oct: Electricity supply back in place and connected to house

11 Oct: Ray helps erect the stairs, above the Consumer Unit

12 Oct: We now have telephone and internet connected as well

13 Oct: Carpenters still here, fitting the kitchen appliances

13 Oct: Bathroom and ensuites starting to be fitted now

16 Oct: Wendy putting in the electric underfloor heating

21 Oct: Ray tiling over the top of the ensuite underfloor heating

21 Oct: Door furniture being attached around the house

22 Oct: Granite for the kitchen being cut and fitted

26 Oct: Painting started, chose Dulux Sandstone for all walls

26 Oct: Ensuite furniture over Ray's tiling is going in

28 Oct: Bannisters fitted to the hallway stairs, no cupboard yet

29 Oct: Kitchen, where the door to the cupboard was to be!

29 Oct: Lighting being fitted - note one base layer of brick

02 Nov: Understairs cupboard now built to house circuit board

03 Dec: New build finished - now to make it a home